A carbon market puts a limit on how much carbon dioxide power stations and factories may emit, and lets them trade the right to emit. Each right is an allowance for one tonne. A company that emits must hand in one allowance for every tonne. So carbon has a price, and that price is part of every gas-fired megawatt-hour.

This article is for anyone joining a power, gas or carbon desk, or building its systems. It explains the UK and EU schemes, how allowances are issued and priced, and what carbon adds to a power station's costs. It covers the changes agreed for 2028, and works through one power station's carbon bill and hedge.

How emissions trading works

Emissions trading is often called cap and trade:

  • The cap. The government sets a total number of allowances for each year, and lowers it over time.
  • The allowances. Each allowance lets its holder emit one tonne of carbon dioxide or its equivalent. Some are given away; most are sold at auction.
  • The surrender. Each year a company reports what it emitted, has the report checked, and hands in that many allowances.
  • The trade. A company that emits less than it holds can sell the spare. One that emits more must buy.

Because the cap falls, allowances get scarcer, and the price gives companies a reason to cut emissions where that is cheapest. For a power station the cheapest cut is often simply not to run.

The UK Emissions Trading Scheme

The UK Emissions Trading Scheme (UK ETS) started on 1 January 2021, when Britain left the EU's scheme. It covers power stations, heavy industry, aviation and, since 1 July 2026, domestic shipping: about a quarter of UK emissions. Plans to add waste incineration in 2028 have been dropped for now. Northern Ireland's power stations are an exception: they stay in the EU's scheme.

  • The cap. The UK ETS issues 936 million allowances in total over 2021 to 2030, falling to about 50 million a year by 2030.
  • The yearly cycle. A company monitors its emissions from 1 January, reports them by 31 March, and surrenders allowances by 30 April for the year before.
  • The penalty. Each missing allowance costs £100, raised with inflation, and the allowance must still be handed in.
  • Auctions. The Government auctions allowances every two weeks, on Wednesdays, on ICE Futures Europe. In 2025, 55,964,500 allowances were available across 25 auctions, and every auction cleared.
  • A price floor. No auction clears below the auction reserve price: £22 in 2025, £28 in 2026 and £29.01 from 1 January 2027.
  • A brake on spikes. If prices rise far above their recent average for six months, the Cost Containment Mechanism lets the Government release extra allowances. It triggered twice, in December 2021 and January 2022, and both times the Government chose not to act.
  • No free allowances for power. Power stations buy every allowance they need. Some industries get part of theirs free, to protect them from cheaper imports.

A UK allowance is called a UKA. On top of it, a power station in Great Britain pays a tax called Carbon Price Support. That is covered below.

The EU Emissions Trading System

The EU Emissions Trading System (EU ETS) started in 2005. It covers power, industry, aviation within Europe and, since 2024, shipping: about 40% of EU emissions.

  • The cap. The 2024 cap was about 1.39 billion allowances. It falls by 4.3% a year to 2027 and by 4.4% a year from 2028.
  • The Market Stability Reserve. When too many allowances are in circulation, the EU takes some out of the auctions and holds them back. The UK has no such reserve; it relies on its price floor and Cost Containment Mechanism.
  • The penalty. €100 for each tonne not covered.
  • A second market from 2028. A separate scheme, ETS2, covers fuel for buildings and road transport. It is fully running from 2028.

An EU allowance is called an EUA. EUAs are auctioned on the EEX exchange in Leipzig, which also runs the auctions for Northern Ireland's power stations.

What allowances cost

These are official figures, each from the government or Commission that runs the market:

2024 2025 2026
UK allowances (UKA) Auctions cleared between £32.10 and £46.92 Auctions cleared between £31.20 and £57.25 Monthly futures averages between £39.46 (March) and £68.26 (January); £63.94 in October
EU allowances (EUA) Auction average €64.74 Auction average €73.43 Quarterly auction averages of €75.36, €75.28 and €82.32, January to September

Converted at the exchange rate, UKAs have mostly been cheaper than EUAs, but no official body publishes the gap between them. Prices move with gas prices, the weather, how much industry is producing, and policy news such as the link agreed in November 2026.

What carbon adds to a power station's costs

A gas plant's carbon cost per megawatt-hour (MWh) of power depends on three numbers:

  • the carbon in its fuel: natural gas emits about 0.18 tonnes of carbon dioxide per MWh of gas burned;
  • its efficiency: a plant that turns half its gas into power burns 2 MWh of gas per MWh of power, and emits about 0.37 tonnes;
  • the carbon price: in Great Britain, the UKA price plus Carbon Price Support.

Carbon Price Support is a tax on the fossil fuels used to make electricity in Great Britain. For gas it is £0.00331 per kWh, which works out at about £18 per tonne of carbon dioxide. It does not apply in Northern Ireland. The Government will remove it from 1 April 2028.

So at an example UKA price of £50, a British gas plant pays about £68 a tonne, or about £25 per MWh of power. Coal emits more than twice as much carbon per MWh of power as gas, so carbon made coal far dearer to run. Britain's last coal plant, Ratcliffe-on-Soar, closed in September 2024.

That carbon cost is one leg of the clean spark spread, what a gas plant earns for running. The spark spread article works it through, and the dark spread article shows what carbon did to coal. Energy market analysis shows how the gas plant's cost sets the British power price most of the time.

What changes in 2028

The UK and EU schemes will link. On 20 November 2026 the UK and the EU concluded a deal to link their emissions trading schemes. Each side will accept the other's allowances, so a British power station could hand in EUAs and a German one UKAs. The two schemes stay separate, each with its own cap, but the allowances become interchangeable. Laws and registries change in 2027. The link is meant to apply from 1 January 2028. The first deadline that accepts both kinds of allowance is 30 September 2028, for 2027's emissions.

Carbon border charges stop between the two. The EU charges importers of carbon-heavy goods for the carbon in them. Its Carbon Border Adjustment Mechanism (CBAM) has been fully in force since 1 January 2026. The UK starts its own CBAM on 1 January 2027, for aluminium, cement, fertiliser, hydrogen, and iron and steel. Under the deal, each side's goods are exempt from the other's charge.

Carbon Price Support ends. From 1 April 2028 British power stations pay only the UKA price. For a modern gas plant that cuts its running cost by about £6.60 to £6.75 per MWh, depending on its efficiency.

For a trader, 2028 changes the cost of every British gas-fired MWh, and ties the UK carbon market to Europe's much larger one. For a systems team, it brings new allowance types in the same registry account. The deal did not cover electricity: Britain's return to Europe's shared power market is still under negotiation, as what Britain loses without coupling explains.

Worked example: Marsh End's carbon

Northfield is an invented trading firm. It owns Marsh End, a 400 MW gas-fired power station that turns 50% of its gas into power. For simple sums we use 0.184 tonnes of carbon dioxide per MWh of gas, a rounded teaching constant. So Marsh End emits 0.368 tonnes per MWh of power. The £50 UKA price is an example, not a market price.

Step 1: September's carbon bill

In September 2026 Marsh End generated 180,000 MWh of power.

Item Working Amount
Gas burned 180,000 MWh x 2 360,000 MWh
Carbon emitted 360,000 x 0.184 66,240 tonnes
UKAs needed 66,240 at £50 £3,312,000
Carbon Price Support 66,240 at £18 £1,192,320
Total carbon cost £4,504,320

The tax can be checked another way: 360,000 MWh of gas is 360 million kWh, and 360 million x £0.00331 is £1,191,600. The two agree to within rounding. Marsh End must surrender the 66,240 UKAs by 30 April 2027.

Step 2: hedging January's carbon

On Wednesday 25 November 2026, Northfield sells 100 MW of Marsh End's power for every hour of January 2027. That is 744 hours, or 74,400 MWh. To lock in the margin, the desk buys the inputs at the same time:

  • the gas: 74,400 x 2 = 148,800 MWh;
  • the carbon: 148,800 x 0.184 = 27,379 tonnes, bought as 27 lots of December 2027 UKA futures. Each lot is 1,000 tonnes; the last 379 tonnes wait until the desk tops up its position.

The December 2027 contract delivers allowances into Northfield's registry account in December 2027. That is well before January's tonnes have to be surrendered.

Carbon Price Support is a fixed tax, about £492,800 on all 27,379 tonnes, so it has no price to hedge. It is simply a cost the desk must include.

The position now has three legs: short power, long gas and long carbon. If any one leg is missing, a move in that price moves the plant's profit. Position aggregation shows how a desk adds the legs up, and energy derivatives explained how the futures work.

January 2027's emissions belong to 2027, the last year before the link starts. Under the deal, 2027's emissions are surrendered by 30 September 2028, not 30 April. If the link is in place by then, Northfield could hand in UKAs or EUAs.

Where carbon trades, and the free data

  • UK allowances trade as futures on ICE Futures Europe, in lots of 1,000 tonnes, priced in pounds per tonne. Delivery is through the UK ETS registry.
  • EU allowances trade as futures on ICE Endex, also in lots of 1,000 tonnes, priced in euros, and are auctioned on EEX.
  • Free data:

What a desk's systems have to track

Carbon looks like one more commodity, but it has its own rules, and a desk's systems have to follow them:

  • Tonnes beside megawatt-hours. Every trade of power and gas has a carbon consequence. The system has to turn generation into tonnes, plant by plant, with each plant's own efficiency.
  • Allowances against emissions. The desk needs to know how many allowances its registry account holds against what it has emitted. It also needs what it will emit under the power it has sold.
  • The deadlines. The surrender date, 30 April today and 30 September once the link starts, is a hard deadline with a fixed penalty.
  • Two kinds of cost. UKAs are a position with a price that moves. Carbon Price Support is a tax at a fixed rate until April 2028. Treating the tax as a position, or the position as a fixed cost, gives the wrong profit and the wrong hedge.
  • The 2028 changes. EUAs become valid for British surrender, and Carbon Price Support disappears from the cost of power.

Building or replacing this on your own desk? It is the work A115 does. See the systems work

What the full guide adds

This article is the short version. The full guide, Interconnectors and Carbon, sets carbon beside the cables that link Britain to Europe:

  • The two schemes side by side, and why UK allowances have traded below EU ones;
  • The Carbon Price Support paradox: the tax raised British power stations' costs, but by pushing coal off the grid it cut demand for UK allowances;
  • How carbon reshapes which plants run, with worked figures;
  • The three-legged hedge in full, with an exercise;
  • CBAM, and how a border charge on carbon works for power;
  • Interconnectors: how power moves between markets and how cable capacity is sold.

The full guide is in the community on Skool, with the rest of the series, and it is updated regularly as the markets change. If you want to work on a trading desk, read it to understand the subject properly. To join, start at the Energy Trading Fundamentals course page.